Metrolinx, the provincial agency in charge of transportation in and around Toronto, filed notice that it could terminate its contract with Bombardier Inc, a spokeswoman said on Thursday, after lengthy delivery delays.

Bombardier in 2010 won a roughly $770 million contract to deliver 182 vehicles between 2013 and 2020. The light-rail vehicles are to be used in a new transit project crossing Toronto due to open in 2021, after Metrolinx pushed back its planned launch by a year.

The pilot vehicle is about two years behind schedule.

"We have taken the next step afforded to us in our contract with Bombardier and I can confirm it's a notice of intent [to terminate]," said Metrolinx spokeswoman Anne Marie Aikins.

Aikins said it was taking the next legal step and did not mean Metrolinx was ending its contract just yet.

In July, the agency filed a notice of default against the Montreal-based plane and trainmaker for delayed delivery of a fleet of light-rail vehicles.

The Toronto Transit Commission has also complained of delayed delivery from Bombardier after receiving only a handful of streetcars it ordered in 2009.

Bombardier spokesperson Marc Laforge told BNN his company isn’t defaulting on its contractual obligations. 

“We don’t understand where Metrolinx is going at when talking about performance on a vehicle that has yet to run its first kilometres on track and production has not started yet,” Laforge said.  